John Wood Court, Bath
Avon Street, Bath
Fire doors & passive fire protection
343 fire doorsets and more than 2,900 recorded fire-stopping installations through six blocks of student rooms, floor by floor.
See our scope
Six blocks of student rooms refurbished floor by floor while the campus stayed in use.
Our work
John Wood Court.
Six blocks, every door, every seal.
CIG Fire Protection installed the fire doors and fire stopping for the phased refurbishment of John Wood Court, the University of Bath’s city-centre student accommodation on Avon Street, working for the main contractor across six blocks from summer 2025.
Blocks A to D took 198 new doorsets (130 bedroom, 46 circulation and 22 bathroom doors) and 2,179 fire-stopping installations at 511 pinned locations on the plans. Blocks E and F followed with 145 doorsets and a further 750 installations recorded to date. Every seal is photographed, pinned to the drawing and logged as installed, and every doorset goes in under our BM TRADA Q-Mark scheme.
- Location
- Avon Street, Bath
- Sector
- Student accommodation
- Doorsets
- 343 (198 blocks A to D, 145 blocks E and F)
- Programme
- June 2025, 15 months
- Fire stopping
- 2,900+ installations recorded
- Scheme
- BM TRADA Q-Mark
CIG Fire Protection / Scope
The package.
Clearly defined.
- 343 new FD30S and FD60S doorsets across blocks A to F, installed and certified under Q-Mark
- 2,179 fire-stopping installations in blocks A to D, each pinned and photographed on the drawings
- 750 more recorded in blocks E and F so far, with the works continuing
- Pipe collars, ablative batts, intumescent sealants and compound to services, joints and voids
- Fire-rated bulkheads, encasements and a fire curtain to the loft as the fire strategy developed